On October 13, Micas Networks announced three 102.4T switches built on Broadcom's Tomahawk 6, including a 1RU co-packaged optics system on Tomahawk 6-Davisson that goes into production in Q1 2027. That announcement is the news. But the number that decides whether CPO gets designed into ordinary data centers came from a lab at Meta, and it is not a bandwidth figure. It is one million.
Meta ran Broadcom's co-packaged optics for one million cumulative 400G-equivalent port device hours without a single link flap, and measured 65% less optics power than pluggable modules. Reliability was the last real objection to putting optics inside the switch package. That objection now has data behind it — for the generation before the one shipping today.
What Meta actually tested
The result was published at ECOC 2025 in a paper titled Co-Packaged Optics Technology Evaluation for Hyperscale Data Center Fabric Switches, and Broadcom announced the milestone on October 1, 2025. The test vehicle was Tomahawk 5-Bailly, Broadcom's second-generation CPO platform: a 51.2 Tb/s switch with the optical engines inside the package, run in Meta's high-temperature lab characterization environment.
Two numbers came out of it. The first is the one everybody quotes: one million cumulative 400G-equivalent port device hours, no link flap. The second is the one that pays for the project: 65% lower optics power per lane against retimed pluggable modules, and roughly 35% lower than linear-drive optics.
The test conditions are worth knowing, because they bound the claim. Meta ran 128 × 400G with every port optically looped back in a 40 °C ambient, logging reliability and performance parameters every five minutes, and did not clear the FEC counters partway through. No failures and no uncorrectable codewords were observed. That is a rigorous validation of the optical link under continuous full-rate load — and it is not telemetry from a live training fabric. One port did misbehave during the run; it traced back to a faulty fiber cable, not the co-packaged optics.
By publication the accumulated figure was 1.05 million cumulative device hours, and the useful detail sits in the margin rather than the failure count: the maximum non-zero FEC interval stayed below 7 on 75% of ports. FEC headroom holding flat over a million hours is stronger evidence than an absence of hard failures, because it shows the links were not quietly degrading toward one.
Note the unit carefully. Port device hours, not wall-clock hours: one port running for a million hours and a thousand ports running for a thousand hours both get you there. That is the right way to measure optics reliability, because it is the aggregate exposure that produces failures — and it is why the number is credible in a way a short demo never is.
Why a link flap is the metric that matters
A link flap is a brief loss of link — a disconnect short enough that it never appears in a dashboard average, and long enough to force a SerDes retrain, a Forward Error Correction (FEC) resync, and a routing reconvergence.
On a storage fabric that is an annoyance. On a training fabric it is a bill. One flapping link stalls the collective that spans it, the step backs up to the last checkpoint, and every GPU in the job waits. At the scale where a single training run occupies thousands of accelerators, the number that shows up in model FLOPs utilization is not peak bandwidth — it is interruptions per hour.
So the honest way to read the Meta data is this: the failure mode that made operators hesitate is the one that was measured, in aggregate, over a long horizon, and it came back at zero.
Read the claim for exactly what it is
This is where most vendor blog posts about the milestone go wrong, so here is the split we would want a customer to hold us to.
It does prove
- CPO links can run for a long, aggregated exposure without a single flap — the core reliability claim, measured rather than asserted.
- Optics power really does fall by roughly two thirds per lane when the DSP leaves the module.
- FEC margin held over the run — maximum non-zero FEC interval under 7 on 75% of ports at 1.05M device hours.
- Meta's paper puts the demonstrated lower bound on link MTBF at a level that can support a 24K-GPU cluster at over 90% training efficiency without the interconnect becoming the bottleneck, and reports roughly 5× fewer failures than pluggable optics on annual link failure rate.
- A merchant switch vendor can ship the same optical architecture a hyperscaler qualified.
It does not prove
- Anything about Davisson. The test was Bailly, at 100G per lane; Davisson runs 200G per lane with new optical engines.
- Field behaviour across many operators. This is high-temperature lab characterization, not years of production fleet data.
- That serviceability is solved — laser replacement, repair turnaround, and sparing are separate problems.
- That CPO is cheaper for every cluster size. The economics turn on port count, reach, and what you would otherwise spend on optics.
Put plainly: the Bailly data is the strongest evidence that the architecture is sound. It is not a warranty on a brand-new optical engine at double the line rate. Anyone selling you the second as the first is skipping a step.
Who did what
This milestone has passed through several hands since the test ran, and the coverage has blurred them together. Here is the split, so you can weigh each part on its own merits rather than taking the whole story at one company's word.
| Party | What they actually own | How this page refers to it |
|---|---|---|
| Meta | Ran the one-million-hour evaluation of Broadcom CPO in its high-temperature lab characterization environment. | Meta's testing, Meta's evaluation |
| Siamak Amiralizadeh | Author of Co-Packaged Optics Technology Evaluation for Hyperscale Data Center Fabric Switches, presented at ECOC 2025 (September 30, 2025) — the primary source for the 1M-hour and 65% figures. | the ECOC 2025 paper |
| Broadcom | Designed the Bailly and Davisson platforms, announced the reliability milestone (October 1, 2025), and published Davisson's specifications and the 70% interconnect-power claim (October 8, 2025). | Broadcom says, Broadcom's release |
| Jabran Kundi, Insider Monkey | The reporting that brought the milestone back into circulation this week, syndicated on Yahoo Finance (October 19, 2026). | Kundi's reporting |
| Micas | Our own power testing (3,267 W vs. 1,626 W), our three 102.4T platforms, and this interpretation — including the six questions below. | Micas testing, our analysis |
From Bailly to Davisson: the generation you can actually buy
Broadcom's CPO program is now on its third generation, with a fourth in development at 400G per lane. The generations are not interchangeable, and the differences are exactly the things that decide whether the reliability result carries over.
Davisson is a different animal from Bailly, and not only in bandwidth. Broadcom's published specification for the BCM78919 puts 102.4 Tb/s of optically enabled switching behind 16 × 6.4 Tb/s Davisson DR optical engines, 200 Gbps per link, 64 × 1.6 TbE ports, and field-replaceable ELSFP laser modules — the last of which quietly answers the serviceability objection that has followed CPO since day one. Optical engines are built on TSMC's COUPE platform and integrated at the substrate level, which is where Broadcom's claim of 70% lower optical interconnect power comes from.
It also has to interoperate, or it is a cul-de-sac. Broadcom specifies Davisson against existing 400G and 800G standards and against DR transceivers, LPO and CPO links at 200G per lane — which means a CPO tier can sit inside a fabric that is not all-CPO.
Why a 1RU CPO switch from a merchant vendor matters
Until now, CPO has been a hyperscaler technology. Meta generated the reliability data because Meta could afford to build the fabric, staff the lab, and wait. Nvidia's Spectrum-X Photonics is now in full production with CoreWeave, Lambda and Oracle among its early adopters — a strong signal, and still a short list.
If you run a colocation fabric, a neocloud, a sovereign AI cluster or a large enterprise training environment, the practical question was never "is CPO better?" It was "can I buy one, from someone who will support it?" That is the gap a merchant 1RU system closes. It changes procurement, not physics.
Micas has been building CPO systems since 2023 and was the first system vendor to commercialize a switch on Broadcom's Tomahawk 5-Bailly platform; that 51.2T CPO switch is now in volume production. The 102.4T generation announced at OCP Global Summit 2026 extends the same approach to Davisson.
102.4T CPO switch
- Silicon
- Broadcom Tomahawk 6-Davisson
- Form factor
- 1RU
- Capacity
- 102.4 Tb/s
- Optics
- 64 × 1.6T MMC DR8
- SerDes
- 200G per lane
- Network OS
- SONiC
- Production
- Q1 2027
Part of a three-platform path. The same 102.4T capacity is available three ways: a 4RU air-cooled switch with 128 ports at 800G, a 2RU liquid-cooled switch with 64 ports at 1.6T, and this 1RU CPO system.
That matters more than the CPO headline. You can start on 800G pluggables with the optics you already own, move to 1.6T as those modules ramp, and adopt co-packaged optics when the power budget or the port count forces it — without changing your network operating system or your operations model.
The power numbers, and why they don't match
You will see three different percentages attached to CPO this month: 65%, 70%, and about 50%. They are all real and none of them measure the same thing, which is why comparing them is how bad business cases get built.
Here is what each one is, and where it came from:
| Claim | What it measures | Measured on | Source |
|---|---|---|---|
| 65% less optics power | Optics power per lane vs. retimed pluggable modules | TH5-Bailly at Meta | ECOC 2025 paper |
| ~35% less than LPO | Optics power per lane vs. linear-drive optics | TH5-Bailly at Meta | Same paper |
| 70% less interconnect power | Optical interconnect power vs. traditional pluggables | TH6-Davisson | Broadcom, Oct 2025 |
| 50.23% less switch power | Whole-system draw at full line rate | Micas TH5 CPO vs. TH5 pluggable, 40 °C | Micas lab |
Ours is the smallest number and the most useful one for a capacity plan, because it is the whole box: switch, optics, fans, everything on the rack feed. A 51.2T Tomahawk 5 switch with 400G DR4 pluggables drew 3,267 W in our testing. The CPO version of the same switch drew 1,626 W, at 40 °C ambient with full line-rate bidirectional traffic.
At 102.4T the arithmetic gets more interesting, not less. The 65% figure is per-lane optics power; two thirds of a large number is still a large number, and doubling the line rate does not double the power budget you have available.
Six questions to ask before you commit
Whether you are talking to us or to anyone else, the same six questions separate a credible CPO proposal from a data sheet with a decimal point in the wrong place.
- Which generation is the data from?A million-hour result on a previous generation is evidence about an architecture. Ask what has been qualified on the part you would actually deploy.
- What is the measured laser failure rate?Meta's result used pluggable laser sources and a lab environment, so it characterises the optics, not laser wear-out in your racks. Ask for a failure rate in FIT or an MTBF, and for the interval you should plan to replace lasers on.
- What happens to the lasers?Davisson specifies field-replaceable ELSFP modules. Confirm your system ships that way and that spares sit where your technicians are.
- What is the optics service model?There is no module to pull out of a port. Ask what the replaceable unit is, what the mean time to repair it looks like, and who does the work.
- What cooling does it need?Our 51.2T CPO switch is an air-cooled 4RU system; the 102.4T CPO platform is 1RU. Make sure the answer matches the racks you have, not the racks you are planning.
- Who owns the software?CPO changes the optics. It should not change the fact that you can run your own network operating system, on SONiC, with your automation on top.
What this means for your next refresh
Two things changed this month, and only one of them was the announcement.
The first is that the reliability objection to CPO now has a million hours of data behind it, from the operator with the most to lose if it were wrong. The second is that the hardware moved from a hyperscaler-only supply chain to a merchant 1RU system with a production quarter attached.
If you're planning a 102.4T fabric for 2027, the decision in front of you isn't "CPO or nothing." It's whether or not your platform vendor can give you 800G pluggables today, 1.6T as it ramps, and co-packaged optics on the same software when your power budget says so. That is a portfolio question, and it is the one worth spending a design review on.
Frequently asked questions
Is CPO reliable enough for production now?
Did Meta test the 102.4T Davisson switch?
What exactly is a link flap?
Do I lose the ability to swap optics?
Why does Micas report 50% when Broadcom reports 65% or 70%?
Planning a 102.4T fabric?
We will walk you through the 800G → 1.6T → CPO path on one SONiC platform, and model the power and optics spend against your port count.